CMP wants to run a new 115 kV line on steel poles up to about 110 feet tall through Cumberland, Falmouth and Portland, plus rebuilt lines in Westbrook and substation work in Yarmouth. We're the neighbors asking one question first: is it really needed?
We're not alone in questioning the need. Maine's Office of the Public Advocate has said CMP's Portland-area forecast may be overestimated. The Public Advocate, the Conservation Law Foundation and the Town of Falmouth all asked the Commission to test CMP's claimed need before anything else (Items 141, 142, 143).
CMP keeps changing its story on why this project is needed.
The need is driven by forecast load growth and aging equipment.
CMP’s exact words: “This study was driven by load growth forecasted in the area and asset condition needs.” Petition, p. 16 ↗
2 · Sept. 2026 · The forecast is challenged
Neighbors and the Public Advocate question the forecast.
Neighbors on the route asked the Commission to test CMP’s forecast first. The Public Advocate agreed: “Solutions based on an unrealistically high load forecast create a risk that the modeled needs will not materialize.” ISO New England has cut its forecast twice since 2024. Motion on Need ↗ · Public Advocate ↗
3 · Oct. 21, 2026 · CMP to Portland councilors
The need is here now, not in a future forecast.
CMP’s exact words: “The customer needs that we’re seeing are today, needed today. They do not rely on projected future growth.” City meeting ↗
The case in 30 seconds
1
Meet the real need. CMP's case rests on a 2024 forecast that later forecasts have cut. The need should be independently confirmed before anything is built.
2
Work out responsible solutions together. Alternate routing, alternate technologies such as undergrounding, and non-wires options deserve a real evaluation.
3
Protect what makes Maine, Maine. Towns north of Portland would carry the towers, the clearing and the construction while receiving little to no benefit.
4
People deserve a real say. Most neighbors learned about this from each other, not from CMP. The case record only reflects what gets filed.
5
CMP keeps changing its story. First, the need came from forecast growth. Now CMP says it doesn't. Which is it?
the full existing right-of-way CMP says it will clear, plus hazard trees 15–20 ft beyond the edge. 150 ft where CMP runs two separate lines.
5
towns on the route; a Phase 2 (South Portland) to follow
2,100+
properties within 1,000 feet of the line
Heights: CMP's petition, Docket 2025-00276 (Sept. 2025), pp. 29–30. Corridor widths: CMP's Sept. 2026 data responses (AP01-001-018, EXM-004-002, ACAUS-001-001, AP01-001-013) and petition Fig. 8; CMP revised its clearing plan in September 2026, and these figures follow its latest filings. Property count: the Alliance's review of public parcel maps, counting every tax parcel whose boundary lies within 1,000 feet of CMP's proposed new or rebuilt line segments across the five towns, each parcel counted once. 1,000 feet is the distance to which the Northern Pass study found measurable value effects.
Is this line really needed?
The forecast behind it has already come down.
CMP built its study on ISO New England's 2024 forecast. The 2025 forecast cut 115 MW from the 2030 summer peak. The 2026 forecast is lower still (Office of the Public Advocate comments, Item 141, Sept. 28, 2026). CMP says none of that changed its design. The landowner intervenors asked the Commission to settle the need question first, and the Public Advocate, the Conservation Law Foundation and the Town of Falmouth backed that request (Items 141, 142, 143). On Oct 9 the Commission's presiding officers ruled that need will be decided in the main case rather than a separate first phase (Procedural Order, Item 155). The landowners will make their case on need in written testimony due Oct 30.
CMP's forecasting practices “raise concerns that the Portland area forecast of load is overestimated, potentially leading to unneeded capital investment.”
What the real need is: reliability
The needs CMP now points to are reliability problems: equipment that wore out and failed.
One worn-out part at the Elm Street substation knocked out power to 28,000 customers on Oct. 9. An 80-year-old line failed in 2023. Fix them. That's upkeep, and it doesn't take a new 115 kV line through people's backyards. CMP's own plan prices rebuilding the old lines and building the new 115 kV line as separate jobs.
CMP makes more money the more it builds.
It earns a return on every dollar it spends on projects like this one. Bigger project, bigger payday. That's why someone independent has to check the need first.
Falmouth is considering the Merrill property, on the north side of the school campus, for a future middle school. CMP's corridor runs through the area, so this project may constrain the Town's own plans for a public school site.
Families in Portland, Falmouth, Cumberland and Westbrook describe the same thing: a thin line of trees is all that separates their yard from the right-of-way. The proposed clearing would remove it, putting the towers in full view from windows and backyards where they aren't today.
Residents have documented poles set back only tens of feet from homes, cleared buffers left as debris after past pole replacements, and a protected vernal pool backing directly onto a yard and the right-of-way. That site-specific detail is easy to miss in a regional filing.
“This project is urgently needed to keep the lights on in Greater Portland.”
CMP's need rests on a forecast now being questioned in the case record. In public comments filed Sept 28 (Item 141), the Office of the Public Advocate wrote that several of CMP's forecasting practices “raise concerns that the Portland area forecast of load is overestimated, potentially leading to unneeded capital investment.” CMP built its study on a 2024 regional forecast that later forecasts have revised downward, and its own witnesses acknowledged some loads “might be” double counted (Technical conference, Item 131; see also OPA, Item 141 at 4). Independently verifying the need is essential before anything gets built.
“There's no real alternative to this version of the project.”
Maine law requires the evaluation of non-wires alternatives such as battery storage and distributed generation (35-A M.R.S. § 3132(2-D); see OPA comments, Item 141 at 5), but the current process only tests whether an alternative can support the need CMP identifies, not whether that need is accurate. Verifying the need could open the door to less destructive solutions, including alternative wire solutions.
“This project is for the public good.”
We're not against investing in Portland's energy future; meeting growing demand is exactly the job CMP should be doing. But this proposal is destructive. CMP is an investor-owned utility that earns a return on what it builds, so it has every incentive to build big and none to find less expensive or less destructive solutions. That conflict of interest is why this needs independent evaluation.
“This project serves 200,000 customers in the Greater Portland area.”
That number describes the whole region, not who benefits. The need behind this project is concentrated in Portland, and it rests on a forecast now being questioned in the record. The towns north of Portland would receive little to no benefit, yet bear the towers, the clearing and the loss of public and private property.
“This won't have a big impact on landowners.”
Independent data from comparable cases in New England (the New Hampshire Northern Pass proceeding) found value loss of as much as 34% on the most directly affected properties. In Falmouth, the proposed route could constrain planning for a future middle school site.
“CMP informed landowners and impacted parties before filing.”
Most residents learned of the project from our door-to-door canvassing and by word of mouth, not from CMP, and only after CMP had filed.
“Clearing the right-of-way just means trimming a few trees.”
CMP's vegetation management plan filed with the Maine Board of Pesticides Control uses herbicide spraying, not just cutting, on a roughly four-to-five-year cycle. Clearing the full width of the right-of-way, plus hazard trees beyond its edge, brings that treatment zone closer to homes, wells, children's play areas, schools and conserved land along this route. Read about the safety concerns we're tracking.
“This is the best solution to meet Portland's future energy needs.”
What gets built now will stand for decades in a hotter, stormier Maine, where the state's own scientists project more than a doubling of wildfire probability. Overhead lines are a fire risk: California's deadliest wildfire was started by a 115 kV line, the same voltage proposed here. Undergrounding and other resilient alternatives are safer and deserve a real evaluation. Read about wildfire and climate risk.
Steel monopoles up to about 110 feet tall, above the tallest oaks in your neighborhood. An audible buzz in stormy and foggy weather. And aggressive clear-cutting of a right-of-way that today is often just a thin line of trees behind the back fence.
Illustrative only. The route, tower design and distances to homes are not final; these are examples, not a prediction for any one property.
CMP has applied for a Certificate of Public Convenience and Necessity to build new and rebuilt high-voltage transmission lines and to expand, build or remove substations across Cumberland, Falmouth, Portland, Westbrook and Yarmouth. In several of these neighborhoods it would be the first time high-voltage transmission has been sited there at all, not an upgrade of a corridor residents already live alongside.
Steel monopoles up to about 110 feet tall (CMP's petition gives an average of 90–110 ft for the new 115 kV line).
A second line through the same corridor: a new 115 kV line beside the existing 34.5 kV line, within the same right-of-way.
Full-width clearing: CMP originally proposed widening parts of the corridor from 100 to 150 feet (petition, p. 35). In September 2026 it told the Commission it has redesigned the project to fit within its existing rights-of-way in most places, and that it expects to clear the full 100-foot width of the existing right-of-way, plus hazard trees about 15 to 20 feet beyond the edge (CMP data responses AP01-001-018, EXM-004-002, ACAUS-001-001, AP01-001-013). Where it runs two separate single-circuit lines, the corridor is 150 feet (petition, Fig. 8). Updated October 2026: CMP's proposal shifted in September, and we've updated these figures to match its latest filings. Updates like this are normal in a proceeding like this one; every figure on this site that comes from CMP follows its filings as they're updated.
Substation work: expansions of Raven Farm (Cumberland) and East Deering (Portland), a new Bayside substation in Portland's East End, and removal of the Elm Street substation in Yarmouth (petition, p. 15).
Cost & timeline
Phase 1, the only phase CMP has filed so far, is a massive, disruptive buildout. A future Phase 2 (a South Portland loop) will follow in a separate filing, so a total scope isn't available yet. The Commission found the application complete in July 2026 and opened a review that could take up to a year; if approved, construction would run 2027 through about 2030–31: three to four years of heavy equipment, clear-cutting and construction traffic.
ILLUSTRATION · ARI technical expertDrawn by ARI's technical expert from the pole types and heights in CMP's petition (pp. 29–30) and CMP's December 2025 open-house boards. The 135-ft clearing width is the Section 180A corridor (petition p. 39). Illustrative, not to scale for any specific property.
See it on the map
The route as CMP's application describes it today: the existing utility corridor, and where the proposed new line would run within it.
Map key
Right-of-way (ROW) boundary. The outer edges of CMP's existing utility easement.
ROW centerline. The midline of the easement.
Rebuilt line. CMP's current 34.5 kV line would be shifted to accommodate the second line and rebuilt with metal poles.
Proposed new line. The new 115 kV line CMP is proposing to add within the same right-of-way, alongside the existing line.
Illustrative impact depiction for the S180, S262, S180A corridor based on publicly available information; not intended as a final survey of impacts. CMP's own project page also includes its route map and town-by-town overview visuals.
Our case before the Commission is about need, cost and process. Separately, as neighbors and parents, many of us are also concerned about what runs through the air above this corridor, what gets sprayed on the ground beneath it, and what happens when overhead lines meet a hotter, stormier Maine.
We're pro-electrification. Portland should get the power it needs. We're not opposed to CMP as a matter of principle; we're asking for more from a public utility.
A coalition of landowners and residents across Falmouth, Cumberland, Portland, Westbrook and Yarmouth, organized under a written charter and participating as formal intervenors in the MPUC docket. Not a petition: a standing organization for legal and organizing purposes. Alliance for Responsible Infrastructure, Inc. is a Maine nonprofit that has filed notice with the IRS to operate as a 501(c)(4), to better advocate on behalf of impacted communities.
We accept that Portland-area energy needs are growing. Our position is that CMP hasn't proven the scale of need it claims, that its proposed solution imposes concentrated harm on communities and the environment in towns north of Portland that will receive little to no benefit from it, when better solutions exist, and that a for-profit company performing a public function can't be trusted to self-correct without independent scrutiny.
Retained an independent technical team to scrutinize CMP's claimed need.
Filed as formal intervenors, with data requests submitted to CMP and a motion asking the Commission to settle need first.
Canvassing door-to-door across all five towns; most residents we've met heard about the project from us or their neighbors, not from CMP.
Working with town councils and school districts on local buffer ordinances and getting documented impacts into the official case record.
Working with State Representatives and Senators to ensure a fair process for our communities.
Represented by outside legal counsel with experience in contested transmission cases.
Did you hear about this project from CMP, or from somewhere else?
One click helps us document notice for the state case.
Thanks, your answer's recorded.
Got 60 more seconds? A few more questions help us document real community impact for the state case. Take the short survey →
Get involved
Key dates, and ways to add your voice.
5 min · Anyone can do this
File a public comment with the PUC
The fastest way to be heard. Your comment goes straight into the official case record for Docket No. 2025-00276. No meeting, no lawyer, and you don't have to be a party. Say who you are, where you live, and how the project as proposed affects you.
Go and demand answers. CMP filed this plan more than a year ago, and most neighbors still heard about it from each other. Now CMP admits "more direct conversations are needed." Make it answer: Where do the poles go? How much gets cut? Why are we only hearing this now?
Oct 19
Portland City Council, 5pm, City Hall
Monday. North Deering neighbors are asking everyone to show up in force and speak during public comment, 3 minutes each. You don't have to live in Portland to speak. Bring neighbors and family; a full room shows the Council how many people this affects. Ask Portland to stand with its neighborhoods: support an independent look at whether this project is needed, and oppose it as proposed.
Monday. Speak at public comment and ask the Town to press CMP for answers.
Oct 30
Written intervenor testimony due
Friday. Moved from Oct 23 by the Commission's Oct 9 order. The Alliance's expert and landowner testimony goes on the record. Send property statements and photos as early as you can; they must reach us well before this date to be included.
Thursday. Elm Street substation is in Yarmouth. Ask the Council to press CMP for answers.
Dec 10
Intervenor technical conference, Hallowell, 9am
Thursday. Moved from Dec 2 by the Commission's Oct 9 order. Live questioning of intervenor testimony by the other parties. In person at 26 Katherine Dr, Hallowell, or streamed.
Docket dates per Docket 2025-00276 filings as of Oct 2026; meeting dates as announced in October 2026. Falmouth, Portland and Westbrook: check posted agendas. The Commission can amend its schedule; confirm on the case portal before you travel. Clerk's office: (207) 287-3831.
We can't make this case without independent technical experts and legal counsel; that's the single biggest thing standing between us and being heard in this docket. We're an all-volunteer effort covering those costs out of pocket.
A rough starting point for your own written statement, not an appraisal. This gives an illustrative range calibrated to case data from the New Hampshire Northern Pass transmission proceeding, not your specific property. For anything filed as evidence of value, a licensed appraiser's opinion carries far more weight.
Within 300 feet, we assume the new towers and the cleared corridor will be visible from your home or yard; steel monopoles up to about 110 feet tall plus full-width clearing of the right-of-way leave little or no screening at that distance.
After the added clearing, will the towers or lines be visible from your home or main yard?
Rough range
—
Enter a property value for a dollar range.
Write this range into your statement as a starting figure, and say plainly that it's your own estimate pending a professional appraisal. Cite the source below if you reference these percentages directly.
Where these ranges come from: the Northern Pass economic impact report by Kavet, Rockler & Associates, prepared for New Hampshire's Counsel for the Public (NH SEC Docket 2015-06, 2016). Read the report (PDF) ↗
The case data we're citing
Kavet, Rockler & Associates, LLC, “Economic Impact Analysis and Review of the Proposed Northern Pass Transmission Project,” prepared for the New Hampshire Office of the Attorney General, Counsel for the Public (not by either side's advocates), NH SEC Docket No. 2015-06 (report filed Dec. 30, 2016; supplemental exhibit Apr. 17, 2017). Headline findings: over $1.1 billion in residential property within the project's viewshed, an estimated $15–30 million in wealth loss to affected owners, and value effects on nearby properties of “15% to as much as 34%, and more for individual properties” in the comparable studies the report reviewed. The report's own distance-and-view model (Tables 16–17) implies losses of roughly 32% for homes with an immediate view of the line, about 9% for a foreground view, and under 1% for more distant views; the authors call it conservative and note significant declines as far as 1,000 feet from the line. The report also cites a U.S. Department of Energy review that applied a 3.5% loss to all properties within 500 feet. Read the report ↗
Document your property for the case record
The Commission only weighs what's actually filed. Send us three things:
1
Photos.A wide shot from your home or main living area toward the corridor; any window, porch, yard or driveway view; trees likely to be cleared; one shot with a person or vehicle for scale.
2
Your property.Acreage, current use (residence, working land, woodland, rental), and notable features: well, septic field, gardens, trails, outbuildings, frontage.
3
The impact, in your words.Use of the land (farming, building, subdividing, timber, recreation); quality of life (views, noise, traffic, privacy); physical changes (cleared trees, grading, access roads, drainage); and your own sense of value, using the estimator as a starting point.
Send photos, your property description and your written statement to our intake account. We'll compile it for submission into the case record and follow up if we need anything else.
Filing deadlines, meeting outcomes and how to help. Sent when there's something worth knowing, not on a schedule.
We'll never share your email. Sends to our organizing team at contact@ariformaine.org.
Sign the petition · Falmouth residents only
To the Falmouth Town Council
We ask you to adopt a 300-foot setback for above-ground high-voltage transmission lines, and a 50-foot setback for underground lines.
Read the full petition text
Central Maine Power has filed for state approval of its Greater Portland Transmission Upgrades Project (Maine PUC Docket No. 2025-00276), a massive, disruptive buildout of new and rebuilt high-voltage transmission lines running through Falmouth, Cumberland, Yarmouth, Westbrook and Portland. Many affected residents were never properly notified before the filing, and the project as proposed would allow new towers and lines to be sited close to homes and school properties with no protective buffer in place today.
The Town Council has already begun looking into this docket, and town representatives have signaled to representatives of our Alliance that they are willing to consider a more active role in protecting landowner rights and the rights of our community. In 2013 the Legislature considered a 300-foot setback for new power lines near homes and schools (LD 950). At the Energy and Utilities Committee's request, the PUC reported that no state required a 300-foot setback, that it would not be feasible for distribution lines, and estimated it could cost about $950 million for CMP's existing transmission system alone. The bill was not enacted (Maine PUC report, Docket 2013-00402, Nov. 30, 2013).
We ask the Town Council to take up and adopt a 300-foot setback for above-ground high-voltage transmission lines, and a 50-foot setback for underground lines, without delay, while the state's review of this project is still underway and before any route or design is locked in.
More resources will be added here as we produce them: fact sheets, boards, expert materials, and anything else useful for canvassing, testimony, or talking to your neighbors.